We were employed to remediate a former animal feed warehouse in Cullingworth for a new housing scheme for Avant Homes, we did a full turnover of the site removing any old relic foundations, lifted the slab area on site and crushed the hard material to then use as back fill for the site, the site was then vibro piled, the job took 11 weeks from November 22 through until end of February.
We were employed by Keepmoat Homes to strip all site vegetation, full site remediation, break up all hard surfaces and process using a crusher to reinstate the site with the processed material, full turnover on site removing any old relic foundations from the former train yard site, build up the levels on site and install piling mats