Another earthworks project successfully completed by the VPH team.

Oaktree Living on Redworth Road, Shildon.

The scope of works included extensive bulk earthworks, beginning with the topsoil strip before carrying out cut and fill operations across the road areas and housing plots. Our team also installed the required piling mats, preparing the site for the next stages of construction.

Another great example of our team delivering a complete earthworks package safely and efficiently.

cullingworth project

Before

after

We were employed to remediate a former animal feed warehouse in Cullingworth for a new housing scheme for Avant Homes, we did a full turnover of the site removing any old relic foundations, lifted the slab area on site and crushed the hard material to then use as back fill for the site, the site was then vibro piled, the job took 11 weeks from November 22 through until end of February.

heaton project

We were employed by Keepmoat Homes to strip all site vegetation, full site remediation, break up all hard surfaces and process using a crusher to reinstate the site with the processed material, full turnover on site removing any old relic foundations from the former train yard site, build up the levels on site and install piling mats

Leeds / Bradford Airport

VPH Earthworks Ltd was the main earthworks contractor for BCE Northern Ltd (Principal Contractor) on the Project for Leeds Bradford Airport (The Client) for a new car parking extension. The works had to be undertaken during the winter months for completion in the spring of this year. As can be seen from the photographs, we worked even during the snow and completed the project on time for the client. The works had been adjacent to the airport runway, and therefore health and safety was a major factor in undertaking the works safely, with the works being completed with no incidents.

The works involved :

  • Site strip of vegetation & topsoil (removed off site)
  • Excavate to reduced level & compact formation
  • Fill using site material
  • Excavate and remove surplus material off site for attenuation tank and compact formation
  • Backfill to attenuation tank
  • Excavate and compact for roads
  • Fill and compact type 1 to roads
  • Install impervious Visqueen, geogrid and cover with 4 -20mm aggregate to parking area (for Bodpave)
  • Grade subsoil ready for topsoiling